REPORT
ON
PROGRESS WITH
PHASE 3 P.S. OSCAR~W
RESTORATION.
The work
on the hull of Oscar W has slowed because of the low water. Oscar had to
be refloated before Christmas so the planks did not dry out too much but
the continuing low water means we cannot get the boat back on the slip.
All other works are proceeding according to plan but the last of the hull
work is holding us up. Alternatives are being investigated but no final
decision has been made as to how we overcome this.
Roly
Bartlett
, (project manager)+